Waterfront Improvements For Wharves K-10 And K-11, FISC, Pearl Harbor
Fleet And Industrial Supply Center, Pearl Harbor, Hawaii
Geotechnical exploration during design, consultation during a Functional Analysis and Concept Design (FACD), consultation during preparation of a parametric cost estimate (PCE) and during post construction award services (PCAS) for waterfront improvements at Wharves K10 and K11 in Pearl Harbor.
Demolition of 73 meters of Wharf K11, and the construction of a new reinforced concrete wharf on precast/prestressed concrete piles to support supply loading and unloading operations.
15.2 meter wide deck, a 12.2 meter wide pile support relieving platform, a 13.7 meter wide concrete hardstand, sheetpile bulkhead, new fender piles and a transit warehouse.